White Tab 114 — Scope Manipulation Evidence Compendium (Facts-Only)

GUARDRAIL: WHITE — FACT REPOSITORY ONLY

Facts & source pinpoints only. No strategy, no argument, no legal opinions. All quotations are "as reported" unless exact text appears in a cited source.


PART A — Purpose and Scope

This document serves as the master evidence reference for the scope manipulation issue at G21 (97 Green Street, Brooklyn). It consolidates:

  1. The Promise — The court-ordered scope of work (Dec 8, 2020)
  2. The Field Instructions — What workers were actually told to do (Jul 2021)
  3. The Certification — What ALC certified as complete (Aug 3, 2021)
  4. The Audit — What independent expert Olmsted found on-site (Aug 18, 2022)
  5. The Admission — Counsel's acknowledgment that affidavits were "not accurate"
  6. The Consequence — Visible mold documented after "clearance" (Jul 2023)

Document Discipline: This is a facts-only compendium. For strategic analysis, see Purple B007-B009. For damages calculations, see Blue/Pink sections.


PART B — The Court-Ordered Scope (The Promise)

Source: WT-108A — Mold Abatement Work Scope (Dec 8, 2020), extracted from ALC PRV Appendix B; also filed as Stipulation Exhibit 1 in HP 6086/2020.

Legal Status: Court-approved and so-ordered as part of Stipulation of Settlement.

B.1 The 10-Item Scope Requirements

Item Location Court-Ordered Requirement Source
1 Studios 1-3 (Rooms 1, 2, 3) Gut demolish: remove walls to studs, floors to concrete slab, ceilings to deck. HEPA vacuum framing; detergent clean. WT-108A §B
2 Bathroom Remove raised floor under tub and water heater. Clean exposed cavities. WT-108A §B
3 Bathroom/Kitchen shared wall Open from bathroom side; HEPA + detergent clean back of kitchen base cabinets and wall cavity. WT-108A §B
4 Hallway Washer/Dryer area Remove units; open wall; HEPA + detergent clean. WT-108A §B
5 Neighbor shared walls Remove to wall cavity (neighbor side). WT-108A §B
6 Room 2 (common hallway wall) Remove lower 4 feet of wall shared with common hallway. WT-108A §B
7 Hallway between Rooms 1-3 Remove ceiling above rooms; remove insulation; clean loft area above; clean deck/joists. WT-108A §B
8 Living room party wall Cut four 24"×24" exploratory probes into wall cavity shared with neighbor; inspect for mold growth. WT-108A §B
9 Living room ceiling Cut probes to wood deck; inspect for mold. WT-108A §B
10 Air handling / HVAC Service unit, clean housings, replace filters. WT-108A §B

B.2 Key Operational Requirements

  • Containment: Regulated work areas with tight containment and negative pressure
  • Worker Protection: PPE per plan; decontamination chamber
  • Cleaning Standard: HEPA vacuum + detergent clean; repeat until visually clean
  • Clearance Condition: Areas must pass visual inspection before air testing

B.3 Margin Comments on Scope Document

The Dec 8, 2020 scope pages contain inline editorial comments attributed to "JG" (Jack Glass):

Tag Comment Text Location
JG1 "Except as noted in 6, below." Item 1 area
JG2 "I would require only 2 feet to expose and examine." Item 6 area

Source: WT-108A §D


PART C — The Field Instructions (The Betrayal)

Source: WT-208 — Raheem Coleman (SERVPRO) Witness Profile, §C.1

Witness: Raheem Coleman, SERVPRO Production Manager, on-site supervisor during July 20-27, 2021 remediation window.

C.1 Coleman's Reported Instructions

Element Court-Ordered (WT-108A) Field Instruction Received (WT-208)
Walls Remove to studs "Only remove one layer of drywall"
Floors Remove to concrete slab "Only the bamboo layer of the flooring system"
Party wall probes Cut four 24"×24" probes "Not mentioned"
Ceiling probes Cut probes to wood deck "Not mentioned"

Attribution: Reported by Christian Gray from on-site conversation with Raheem Coleman during July 20-27, 2021.

Status: As reported; native Coleman statement not yet collected. Collection task: COLEMAN-LOCK-01.

C.2 The Categorical Divergence

The divergence is not technical or ambiguous — it is categorical:

Requirement Type Court Order Field Instruction Nature of Divergence
Wall removal depth To studs (complete removal) One layer only (surface removal) Fundamental difference
Floor removal depth To slab (complete removal) Bamboo wear layer only (surface removal) Fundamental difference
Party wall probes Required (4 probes) Not mentioned (omitted entirely) Complete omission
Ceiling probes Required Not mentioned (omitted entirely) Complete omission

PART D — The Certification (The False Clearance)

Source: WT-108 — ALC Post-Remediation Verification (PRV), inspection Jul 28, 2021, report Aug 3, 2021.

D.1 PRV Timeline

Date Event Source
Jul 20-27, 2021 SERVPRO remediation execution (7 days) WT-106 §D
Jul 28, 2021 ALC PRV inspection (1 day after work ended) WT-108
Aug 3, 2021 ALC PRV report issued WT-108

D.2 PRV Certifications

The ALC PRV stated:

"This apartment has achieved clearance."

"ALC found apartment to be free and clean of moisture, microbial growth, and 'mold-like' odors."

"Walls removed as per work scope"

"Ceiling removed as per work scope"

"Floor removed as per work scope"

"Building materials measured dry."

Signatories: Candice A. Kowalewski, MPH; Jack Glass, MS, CIH

Source: WT-108

D.3 PRV Timing Issue

The PRV inspection occurred one day after SERVPRO work concluded. A comprehensive scope requiring removal to studs/slab/deck across multiple rooms would typically require more than 7 days to execute and more than 1 day to verify.


PART E — The Professional Audit (The Exposure)

Source: WT-109 — Olmsted Response to ALC (Aug 18, 2022)

Expert: Edward A. Olmsted, CIH, CSP, NYS Mold Assessor

E.1 Executive Finding

"The affirmation is replete with misleading and incorrect statements from Counsel Skaller, Candice Kowalewski and Jack Glass to the degree that it brings into question the veracity of the entire document."

Source: WT-109 §B

E.2 On-Site Inspection Findings (Aug 2022)

Olmsted conducted a physical walkthrough of G21 approximately 13 months after the PRV "clearance" and documented the following:

Scope Item Court Requirement Olmsted Finding (Aug 2022) Source
Item 1 (Studios 1-3) Gut demo to studs; floors to slab; ceilings to deck Only one layer of wallboard removed; much left in place; ceilings above tiles left; Studio 1 floor not removed to slab; framing couldn't be cleaned where wallboard remained WT-109 §D
Item 2 (Bathroom floor) Remove raised floor under tub/HW heater Not done WT-109 §D
Item 3 (Bath/Kitchen wall) Open and clean shared wall Not done; visible mold remained WT-109 §D
Item 5 (Neighbor walls) Remove to wall cavity Not taken to cavity WT-109 §D
Item 6 (Room 2 hallway wall) Remove lower 4 ft Incomplete; visible mold remained WT-109 §D
Item 8 (Party wall probes) Cut four 24"×24" probes Not cut WT-109 §D
Item 9 (Ceiling probes) Cut probes to wood deck Not cut WT-109 §D

E.3 Studio 1 Floor — Detailed Finding

"Two layers of wood floor left in place (not anchored to slab); could be lifted by hand; upper side damp; underside heavily moldy and wet on meter probe."

"Studio 1 floor was to be removed to the slab; he concludes scope was never followed."

Source: WT-109 §C

E.4 Blue Insulation Panels — Detailed Finding

"Panels left in place could be slid aside by hand; doing so revealed visible mold on sheetrock above and on the shared wall."

"The sheetrock ceiling/walls in Studio 1 were to be removed."

Source: WT-109 §C

E.5 Moisture Testing Standard

"Post-abatement inspection should include moisture testing under NYS DOL/NYC guidance; he states ALC did not do this."

Source: WT-109 §C

E.6 Professional Standards Cited by Olmsted

Authority Standard Cited Source
EPA Hidden mold locations; "dead mold" still triggers reactions; removal required WT-109 §F
AIHA (2019) Hidden growth should be effectively cleaned/removed WT-109 §F
Pessi et al. (2002) Growth in insulated walls can degrade indoor air quality WT-109 §F
Local Law 61 of 2018 Required filings (Work Plan Notification, Work Plan, Post-Remediation Assessment Form, Post-Remediation Certification) were not filed WT-109 §H

PART F — The Admission (The Confession)

Source: WT-106 §C; HP 6086/2020 transcript (page/line TBD — collection task HP-TRANS-01)

F.1 The Statement

Defendant's counsel (David Skaller) stated on the court record that the affidavits asserting comprehensive completion were "not accurate."

F.2 Significance

This statement constitutes an acknowledgment by opposing party's counsel that the certifications filed with the court did not accurately represent what was actually done.


PART G — The Consequence (The Real-World Proof)

Source: WT-111 — July 2023 Re-Flood Email Packet

G.1 Timeline

Date Event Source
Jul 12-17, 2023 Re-flood / re-wet event at G21 WT-111
~23 months Time elapsed since "achieved clearance" PRV Calculated

G.2 Conditions Documented

  • Visible mold documented on surfaces that had been certified as remediated
  • Bathroom floor/walls re-wetted
  • Adjacent kitchen/hallway affected
  • Living area ceiling leak during heavy rains
  • Plumber valve break + capping acknowledged
  • Building-wide roof leak pattern reported

G.3 Evidentiary Significance

The July 2023 re-flood documented visible mold in the same areas that the PRV had certified as "free and clean." If the court-ordered scope had been executed — walls to studs, floors to slab, probes cut — the conditions Olmsted documented in 2022 and the visible mold in 2023 could not have existed.


PART H — Consolidated Timeline

Date Event Document Significance
2020-12-08 Court-ordered scope agreed (Stipulation Exhibit 1) WT-108A THE PROMISE
2021-07-20 to 07-27 SERVPRO remediation execution (7 days) WT-106, WT-208 Work performed with reduced instructions
2021-07-28 ALC PRV inspection (1 day after work) WT-108
2021-08-03 ALC PRV report: "achieved clearance" WT-108 THE FALSE CERTIFICATION
2022-08-18 Olmsted on-site inspection + response WT-109 THE PROFESSIONAL AUDIT
2022-11-07 Olmsted follow-up scope proposal WT-110 Additional work identified
2022 (date TBD) Counsel admits affidavits "not accurate" HP 6086/2020 THE ADMISSION
2023-07-12 to 07-17 Re-flood; visible mold documented WT-111 THE CONSEQUENCE

PART I — Source Divergences Matrix (Preview)

Topic ALC PRV (WT-108) States Olmsted Response (WT-109) States
Studio 1 walls/ceiling/floor "Removed as per work scope"; area "free and clean of VMG or odors" Floor not removed to slab; two layers wood left, damp/wet underside with visible mold; sheetrock above insulation and shared wall with visible mold; scope "was never followed"
Material condition "Building materials measured dry." Indoor RH ~73% Moisture present under Studio 1 floor; issues detectable without cutting (lifted/moved by hand)
Overall outcome "This apartment has achieved clearance. ALC found apartment to be free and clean of moisture, microbial growth, and 'mold-like' odors." Multiple scope items incomplete; mold materials left; cites standards and Local Law 61 filings "not done"

Note: Full divergences matrix maintained in WT-114 — Source Divergences Index.


PART J — Key Personnel

Name Role Affiliation Documents
Edward A. Olmsted, CIH, CSP Independent Mold Inspector (Tenant's expert) Olmsted Environmental Services WT-107, WT-109, WT-110
Candice A. Kowalewski, MPH PRV signatory ALC Environmental WT-108
Jack Glass, MS, CIH PRV signatory; margin comments on scope ALC Environmental WT-108, WT-108A
Raheem Coleman On-site SERVPRO supervisor SERVPRO West Somerset County WT-208
Ronnie Garcia SERVPRO lead/estimator SERVPRO WT-207
David Skaller, Esq. Landlord's counsel; "not accurate" statement WT-106 §C

PART K — Collection Tasks (Evidence Strengthening)

Task ID Target Purpose Status
COLEMAN-LOCK-01 Coleman formal statement Lock "one layer / bamboo only" testimony Pending
SUBP-SERVPRO-01 SERVPRO work orders/logs (Jul 20-27, 2021) Documentary proof of scope instructions Pending
HP-TRANS-01 HP 6086/2020 certified transcript Page/line for "not accurate" admission Pending
109-EVID-01 Olmsted photos/moisture data from Aug 2022 Physical evidence of non-completion Pending
111-META-01 Native photos with EXIF from Jul 2023 Authenticate re-flood documentation Pending

PART L — Cross-References

Document Relationship
WT-106 Scope comparison matrix (Court-Ordered vs. Executed)
WT-107 Olmsted baseline inspection (Jun 28, 2020)
WT-108 ALC Post-Remediation Verification (Aug 3, 2021)
WT-108A Dec 8, 2020 Mold Abatement Scope (extracted)
WT-109 Olmsted Response to ALC (Aug 18, 2022)
WT-110 Olmsted Follow-Up Scope (Nov 7, 2022)
WT-111 July 2023 Re-Flood Email Packet
WT-208 Raheem Coleman Witness Profile
Purple B007 Scope Manipulation Criminal Referral Package
Purple B008 Scope Manipulation Courtroom Summary
Purple B009 Scope Manipulation Settlement Playbook

END — White Tab 114 — Scope Manipulation Evidence Compendium (Facts-Only) v1.4